IBBI Valuers guide: Under construction flat home loan valuation: stage visits, RERA and delays

For a flat still being built, the lender values it at sanction and then checks progress before each payment to the builder. Here is how stage-linked disbursal works and what protects you.

In short
  • RBI bars lenders from paying the whole loan upfront for a flat that is not yet built.
  • The lender's engineer checks progress before each payment to the builder.
  • RERA makes the builder keep 70% of buyers' money in a separate account, drawn down as work progresses.
  • If demands run ahead of the work, the lender may hold back, and you pay the gap yourself.

Under construction flat home loan valuation happens more than once. The lender values the flat at sanction, based on your agreement and the project. Then its engineer or valuer visits at each stage of construction before the next payment goes to the builder. RBI does not allow lenders to pay the whole loan upfront for a flat that is not yet built.

Why the loan is paid in stages

RBI’s directions require banks to link disbursal of individual home loans closely to the stages of construction. Disbursal means the release of loan money. Lenders must not pay upfront for incomplete, under construction or greenfield projects. A greenfield project is one where building has not yet begun.

RBI explained its concern. Some lenders had paid whole loans to builders upfront, while the builder paid the buyer’s instalments for a period. These were often called 80:20 or 75:25 schemes. If the builder stopped paying or the project stalled, the buyer was still liable for the loan.

Housing finance companies have similar rules. They must link disbursal strictly to construction stages. They must not offer products where the builder services your loan. They must watch progress and get your consent before paying the builder.

One exception applies. For projects sponsored by a government or statutory authority with no history of unfinished projects, lenders may follow the authority’s payment schedule.

How the flat is valued at sanction

At sanction there is no finished flat to inspect. The valuer works from:

  • the agreement for sale and the payment plan;
  • the project’s RERA registration and approved plans;
  • the carpet area in the agreement;
  • recent sales of similar flats in the project and nearby;
  • the progress on site on the day of the visit.

At a housing finance company, the value used for the loan on a first purchase cannot exceed your agreement price. Stamp duty and registration are left out of the cost at banks and housing finance companies alike. Many lenders also review a project as a whole before they fund buyers in it. That review is a lending decision, not a promise that the project will finish.

Check the carpet area closely. See carpet area vs built-up area. For how new and ready flats compare on price and risk, read under construction vs ready to move.

What the engineer checks at each stage

Before each release, the lender’s engineer or valuer visits and reports on progress. A stage report usually covers:

  1. Stage reached. Foundation, each slab, brickwork, plaster, finishing and so on.
  2. Share of work done. For the tower and, where possible, your floor.
  3. Match with the demand. Whether the builder’s demand letter fits the work actually done.
  4. Quality and deviations. Visible defects and any change from the approved plan.
  5. Photographs. Dated, of the tower and of your unit where it can be reached.

A demand letter is the builder’s request for the next instalment. If the demand runs ahead of the work, the lender may hold or cut the payment. The technical side of these visits is explained in technical verification for a home loan.

Building your own house on your plot works differently. See construction stage certificate for a loan.

RERA checks that protect you

RERA, the Real Estate (Regulation and Development) Act, 2016, adds protections of its own:

  • Registration. Check the project’s page on your state RERA website before you sign.
  • The 70% account. The builder must keep 70% of the money collected from buyers in a separate bank account. It can be used only for land and construction costs.
  • Withdrawals match progress. Money can come out only in proportion to the work completed. An engineer, an architect and a chartered accountant must each certify that.
  • The 10% advance limit. The builder cannot take more than 10% of the cost as an advance before a registered agreement for sale.

The lender’s stage visit and the RERA certificates are separate checks. Both are worth reading.

Payment plan vs construction progress

Payment planWhat it meansHow it fits stage-linked lending
Construction-linkedInstalments fall due as stages finishMatches how lenders release money
Time-linkedInstalments fall due on fixed datesDemands can run ahead of work; the lender still pays by stage
Down paymentMost of the price upfront, often for a discountYour own money must go in first; the lender cannot pay upfront

If the builder’s demands outrun the lender’s releases, you pay the gap from your own funds. Check the payment plan against the lender’s rules before you sign.

Ask the lender three questions at the start. Does it already fund other buyers in this project? How often will its engineer visit? Will it tell you in writing when it holds back a payment, and why?

Pre-EMI and the cost of a long build

Until the full loan is paid out, you usually pay only interest on the amount released. This is pre-EMI interest. Full instalments, covering interest and principal, start once disbursal ends, unless you choose to start earlier. A delay means more months of pre-EMI. If you rent meanwhile, it also means more months of rent.

Worked illustration

You book a flat in Thane for ₹80 lakh on a construction-linked plan. The lender sanctions ₹60 lakh. Your own share is ₹20 lakh.

  • Booking: you pay ₹8 lakh, the 10% advance, from your own funds.
  • Plinth complete: the builder asks for ₹12 lakh. You pay it yourself, which completes your ₹20 lakh share.
  • Fourth slab: the builder asks for ₹8 lakh. The engineer confirms the stage, and the lender releases ₹8 lakh.
  • Later slabs and finishing: the lender releases the rest, stage by stage, after each visit.

You pay pre-EMI interest on each amount as it is released. (Figures are an illustration only.)

If construction stalls

  • The lender stops releasing money until work resumes.
  • You keep paying interest on what has already been released. Missed payments hurt your credit record, whatever the builder does.
  • Ask the lender for its latest stage report. It records how far the work got.
  • Check the RERA project page for progress updates and complaints.
  • Speak to a lawyer about a RERA complaint if the delay drags on.

A low or held-back valuation at any stage can also stretch your own budget. See why bank valuation is lower than market value.

Buying into a project that is still being built? Send us on WhatsApp the project name, its RERA number, your agreement and the builder’s latest demand. We can check whether the price fits the market and whether the work on site matches the demand. Our bank loan valuation page explains how we work, and the fee is fixed and quoted upfront.

FAQ

Questions on this topic

Will the bank pay the builder in one go for an under construction flat?

No. RBI's rules require lenders to link payments on individual home loans to the stages of construction. Upfront payment is not allowed for incomplete or under construction projects. The one exception is a project sponsored by a government or statutory authority with no history of unfinished projects. There, the lender may follow the authority's payment schedule.

Who checks construction progress before the bank pays?

An engineer, architect or valuer appointed by the lender visits the site. They confirm the stage reached and compare it with the builder's demand letter. Housing finance companies must also monitor progress and get the borrower's consent before paying the builder. If the work is behind the demand, the lender can hold or reduce the payment.

Can the bank value the flat below my agreement price?

Yes. The valuer looks at sales of similar flats in the project and nearby. If those are lower than your price, the value adopted will be lower too. At a housing finance company, the value for the loan also cannot go above the agreement price. Stamp duty and registration are left out of the cost in either case.

What is pre-EMI interest?

It is the interest you pay on the part of the loan already released, while the flat is being built. Full instalments, which repay principal as well as interest, usually start once the whole loan is paid out. Some lenders let you start full instalments earlier. A long delay means more months of pre-EMI with no fall in what you owe.

What happens to my loan if the builder stops work?

The lender stops releasing money until work resumes. You still owe what has already been paid out, with interest. Ask the lender for its latest stage report, which records how far work got. Check the project's page on your state RERA website for updates and complaints. A lawyer can advise on a RERA complaint if delays continue.

Free first answer

Not sure which report you need?

Send the property location and what the report is for. A valuer replies with the right report, the papers to collect and one fixed fee. Asking costs nothing.

WhatsApp +91 98913 68886 · Mon to Sat, 10:00 to 19:00 IST

Not sure which report? Mon to Sat · 10am to 7pm
Ask a valuer