A redevelopment feasibility report shows whether rebuilding your society’s building works, and what members can expect from it. It works out how much can be built on the plot, how that area is shared and what it costs. It also estimates what the sale flats will earn. Under Maharashtra’s 2026 order, the society’s architect or PMC prepares it before the tender. Members should read it closely, because every offer is judged against it.
Who prepares it, and when
On 30 September 2026, Maharashtra issued a new order under section 79A of the Maharashtra Co-operative Societies Act, 1960. It replaced the 2019 redevelopment directives. As reported, the order sets out these steps for the report:
- The general body invites quotations from architects or PMCs. Summaries say at least three should be invited.
- A special general meeting picks one. The appointment letter goes out within 30 days.
- The architect or PMC prepares the project report within about two months.
- Members can see it and send suggestions.
- The general body approves the tender draft based on it.
PMC stands for project management consultant. Our guide on the PMC role in redevelopment explains how the PMC, architect and valuer differ. News summaries of the order vary on some details, so read the order itself with your lawyer.
What the report should cover
A useful feasibility report answers these questions:
- Title and plot area. What land does the society own, as per the conveyance deed, property card and approved plan?
- Planning rules. Which rules apply, such as DCPR 2034 in Mumbai or the Unified DCPR in Thane and Pune? What is the road width in front?
- Buildable area. How much floor area can be built, counting basic FSI, premium FSI, TDR, fungible area and any incentive?
- Existing members. How many flats, shops and garages are there, and what is each one’s carpet area?
- Members’ entitlement. What extra area each member could get under different options.
- Sale area. What is left for sale after members’ flats and common areas.
- Design basics. Parking, open space, amenities and construction specification.
- Costs. Construction, premiums, TDR, approvals, rent, corpus, finance and contingencies.
- Revenue. The assumed sale rate for new flats, and the total it brings in.
- Time and risk. How long approvals and building will take, and what could go wrong.
Our guide on how much extra area in redevelopment explains FSI, TDR and incentive area in plain terms.
The numbers behind it
Most reports follow the same logic. They start from the plot and end with what members can be offered:
- Total buildable area, from the plot area and planning rules.
- Less members’ existing area, the rehab area.
- Less common areas, which are not sold.
- That leaves the sale area.
- Sale area times the sale rate gives revenue.
- Revenue less all costs leaves a surplus.
- Part of that surplus is the developer’s fair return. The rest can go to members as extra area, corpus or both.
Every step depends on the one before. A wrong plot area or sale rate flows all the way down.
Test the sale rate first
The sale rate is the number members can least check for themselves. It also moves the result the most.
Say a report assumes 20,000 sq ft of sale area at ₹18,000 per sq ft. Revenue is ₹36 crore. Costs come to ₹30 crore, leaving ₹6 crore. Now say new flats nearby really sell at ₹16,200, which is 10% lower. Revenue falls to ₹32.4 crore, and the surplus drops to ₹2.4 crore. A 10% change in one rate cuts the surplus by 60%. (Figures are an illustration only.)
So ask where the sale rate comes from. It should rest on registered sales in new buildings close by, not on asking prices or brochures. An independent society redevelopment valuation tests it against those sales.
Check the costs too
Costs are easier to overlook than to get wrong on purpose. Check that the report includes:
- Construction cost for both members’ flats and sale flats, at current rates. Our guide on construction cost per sq ft in India explains what drives it.
- Premiums payable to the municipal body and the cost of TDR.
- Rent for members for the whole build, with a margin for delay.
- Corpus, if any, and stamp duty on the agreements.
- Finance costs and a contingency.
A report that leaves out costs makes every offer look generous. A report that pads costs makes members accept too little.
The building’s condition
The report should say whether the building has had a structural audit. A structural engineer checks the frame, slabs and columns and reports on safety. This tells members how urgent the rebuild is, and whether repair is a real option. Our guide to the structural stability certificate explains what engineers check.
Feasibility for self-redevelopment
In self-redevelopment, the society acts as its own developer. The report must then go further. It needs a cash flow plan, a loan amount and a sales plan for the extra flats. Housing society rules amended in June 2026 reportedly link how much a society may borrow for self-redevelopment to its land value. That value comes from a government-approved valuer’s report. So the feasibility report and the land valuation should use the same facts. See our guide to self-redevelopment.
How members should review it
Members often get the report a few days before a meeting. Use that time well. Here is who can check each part:
| Part of the report | What to check | Who can help |
|---|---|---|
| Plot area and title | Matches the conveyance deed and property card | Society’s lawyer |
| Buildable area | Correct rules, road width and incentives applied | A second architect, if in doubt |
| Members’ areas | Each flat measured in carpet area | Members themselves, or a valuer |
| Sale rate | Backed by registered sales of new flats nearby | Independent valuer |
| Costs and time | Current rates, delay margin, all premiums | Engineer or second PMC |
Send your questions to the committee in writing before the meeting. Ask for written answers too. If several members share a doubt, ask the general body to get an independent check before the tender is approved. The order gives members the right to inspect project reports and tender papers, as reported. Use it.
Red flags in a feasibility report
- Plot area taken from old papers, with no check against the property card.
- Areas given in built-up terms while offers speak of carpet area.
- A sale rate with no sale evidence behind it.
- No allowance for delay, rising rents or rising costs.
- A report paid for by a developer who is also bidding.
Received your project report? Send it to us on WhatsApp with the society’s address. We will tell you which figures a redevelopment valuation can test, and quote a fixed fee.