IBBI Valuers guide: PMC role in redevelopment: how the PMC, architect and valuer differ

A PMC runs the redevelopment for the society. An architect designs it. A valuer puts an independent value on what members own and what they are offered. Here is who does what.

In short
  • A PMC acts for the society through the whole project, from the project report to possession of new flats.
  • The architect designs the building and gets approvals. Many PMC firms include an architect.
  • A valuer gives independent values of land, flats and offers. A valuer does not run the project.
  • Under the 2026 order, the general body appoints the architect or PMC from quotations, as reported.

The PMC role in redevelopment is to act for the society through the whole project. A PMC, or project management consultant, leads the project report, runs the tender and compares bids. It helps with the agreements, then tracks the developer’s work until members get their new flats. The architect designs the building and gets the plans approved. A valuer does neither. A valuer gives independent values of the land, each flat and each offer, so members can test the plan.

What a PMC does

A PMC’s work runs from the first meeting to possession. The scope depends on the appointment letter, but it usually covers these stages:

  1. Project report. Working out what can be built on the plot, and what members could get. Our guide to the redevelopment feasibility report explains its contents.
  2. Tender. Drafting the tender papers and terms, and advertising for bids.
  3. Bid comparison. Putting bids side by side and explaining them to members.
  4. Agreements. Working with the society’s lawyer on the development agreement and the PAAAs, the members’ individual agreements.
  5. Approvals. Tracking plans, permissions and the start of work.
  6. Construction. Checking progress, quality and the developer’s promises.
  7. Handover. Checking the new flats against the agreed areas and specifications.

A good PMC keeps members informed at each stage. It answers to the society, not to the developer.

What the architect does

The architect designs the new building within the planning rules. In Mumbai, that means DCPR 2034. In Thane, Navi Mumbai and Pune, it usually means the Unified DCPR. The architect works out the floor area the plot can carry, plans the flats and parking, and gets the plans approved by the municipal body.

Many PMC firms have architects on staff, so one firm may do both jobs. Some societies hire an architect for the report and a PMC for the rest. Either way, check who signs the plans and who is answerable for each task.

Two more experts often join the team. A structural engineer audits the old building and designs the frame of the new one. A lawyer checks the society’s title and drafts the agreements. The PMC usually coordinates their work, but each signs for their own part.

What a valuer does, and does not do

A valuer gives an opinion of market value, signed and backed by evidence. In a redevelopment, that can mean:

  • The value of the society’s land and building today.
  • The value of each member’s flat, on measured carpet area.
  • A check of the sale rate used in the project report.
  • A rupee value for each offer, so they can be compared.
  • Values members need later for tax, such as the old flat’s 2001 value.

A valuer does not design, run tenders, negotiate with developers or watch the building work. We are valuers, not PMCs or architects. Our value is useful because we have no part in the project.

Side by side

QuestionPMCArchitectValuer
Main jobRuns the project for the societyDesigns and gets approvalsGives independent values
When involvedStart to possessionReport, design and approvalsBefore the vote, and when members need values
Prepares the project reportYes, or leads itOftenNo, but can test it
Runs the tenderYesSometimes helpsNo
Values land, flats and offersGives estimates in the reportNoYes, as a signed opinion
Watches constructionYesChecks against approved plansNo

How a PMC is appointed under the 2026 rules

On 30 September 2026, Maharashtra issued a new order under section 79A of the Maharashtra Co-operative Societies Act. It replaced the 2019 directives. As reported, the order sets out these steps:

  • The society invites quotations from architects or PMCs. Summaries say at least three.
  • A special general meeting chooses one, with the required quorum and votes.
  • The appointment letter goes out within 30 days.
  • The project report is due within about two months of appointment.

Housing society rules amended in June 2026 also cover meeting notice, quorum and video records. News summaries differ on some details, so read the order with your lawyer.

Watch for conflicts of interest

A PMC has influence over which developer wins. So the society should check for conflicts before hiring:

  • Has the PMC worked for any of the bidding developers?
  • Does the fee depend on which developer wins, or on the size of the project?
  • Will the developer later bear the PMC’s fee? If so, when, and does the PMC still answer only to the society?
  • Is the PMC also offering to value the flats? Keep that role separate.

An independent valuer helps here too. A value from outside the project tests the PMC’s numbers without any stake in the result.

The PMC on the self route

In self-redevelopment, the society builds for itself with a contractor and a bank loan. There is no developer to manage the work. So the PMC’s job grows. It helps choose the contractor through the tender. It checks bills before the society pays them. It tracks costs against the budget and reports progress to the bank. It also helps plan the sale of the extra flats.

That makes the choice of PMC even more important. A weak PMC on the self route costs members money directly, because they carry the risk. Our guide to self-redevelopment of a housing society explains the model.

What to put in the appointment letter

The appointment letter is the PMC’s contract. Make sure it covers:

  • The exact list of tasks, stage by stage.
  • The fee, how it is paid, and what happens if the project stops.
  • Who from the firm will do the work and attend meetings.
  • How often the PMC reports to members, and in what form.
  • A promise to disclose any past or present work for bidding developers.
  • How the appointment can end if the society is not satisfied.

Keep a copy with the society’s records, and share it with members.

Questions to ask before you hire a PMC

  1. Which societies have you handled, and can we speak to their committees?
  2. Who in your team will attend our meetings and visit the site?
  3. What exactly is in your scope, and what costs extra?
  4. How will you report progress to members during construction?
  5. How do you deal with a developer who misses deadlines?

For engineering and valuation roles more widely, see chartered engineer vs registered valuer. Our guide to society redevelopment valuation shows where a value fits in the process.

Has your society appointed a PMC and received a project report? Send it to us on WhatsApp with the society’s address. We will explain what an independent redevelopment valuation would check, and quote a fixed fee.

FAQ

Questions on this topic

What does a PMC do in society redevelopment?

A PMC, or project management consultant, acts for the society through the project. It prepares or leads the project report, drafts the tender, compares bids and helps with the agreements. It then tracks the developer's work, approvals and promises until members get their new flats. The exact scope is whatever the society's appointment letter says.

Is a PMC compulsory for redevelopment?

The 2026 order, as reported, requires the society to appoint an architect or PMC to prepare the project report before the tender. It does not require a separate PMC on top of an architect. Many societies still hire a PMC for the whole project, because members rarely have time to track approvals and construction themselves.

Can the PMC also value our flats?

It is better to keep the roles apart. The PMC plans the project and advises on bids, so it has a view on the outcome. A valuation should come from someone with no part in the project. The society then has an outside check on the land value, sale rates and offers that the PMC's report relies on.

Who pays the PMC's fee?

The society appoints the PMC and agrees the fee. In some projects, the agreement later makes the developer bear that cost. Either way, the PMC should act only for the society. Ask how the fee is paid and whether it depends on which developer wins, before you sign the appointment letter.

Do we need a valuer if we already have a PMC and an architect?

You do not have to have one, but it helps. The architect and PMC work out what can be built and what members can expect. A valuer tests those numbers against the market. That matters most for the sale rate in the project report and for comparing offers before the vote.

Free first answer

Not sure which report you need?

Send the property location and what the report is for. A valuer replies with the right report, the papers to collect and one fixed fee. Asking costs nothing.

WhatsApp +91 98913 68886 · Mon to Sat, 10:00 to 19:00 IST

Not sure which report? Mon to Sat · 10am to 7pm
Ask a valuer