NHAI land acquisition compensation is fixed under the National Highways Act, 1956, not the usual 2013 land acquisition Act. A government officer, called the competent authority, values the land as on the date of the section 3A notification. In this guide we call it the officer. Since 2015, the 2013 Act’s compensation rules also apply, so rural land gets a factor of up to 2 and 100% solatium is added. If you do not accept the amount, you can apply for arbitration.
NHAI is the National Highways Authority of India. The same law also covers highway land taken for other agencies building national highways.
How a highway acquisition runs
The National Highways Act sets a faster process than the general law. These are the main steps:
- Section 3A notification. The Central Government announces that it intends to acquire the land, with a short description.
- Objections, section 3C. Anyone interested can object to the use of the land within 21 days.
- Declaration, section 3D. Once objections are dealt with, a declaration is issued. The land then belongs to the Central Government, free of all burdens. If no declaration comes within a year, the 3A notice lapses.
- Public notice, section 3G. The officer puts a notice in two local papers, one in the local language. It invites claims from everyone with an interest in the land.
- Amount fixed. The officer fixes the amount in a written order.
- Deposit and payment, section 3H. The money is placed with the officer before the land is taken, and then paid out.
- Possession, section 3E. You can be given 60 days’ notice to hand over the land.
Ownership passes at the declaration, before the amount is fixed. So your claim at step 4 matters a great deal.
How the amount is set
Section 3G(7) lists what the officer or the arbitrator must weigh:
- the market value of the land on the date of the section 3A notification;
- damage from cutting the land off from your other land;
- harm to your other property or your earnings;
- reasonable costs of moving your home or business.
Since 1 January 2015, the 2013 Act’s First Schedule applies to highway land too. That brings in four rules: market value under section 26, the rural factor of 1 to 2, the value of buildings, and 100% solatium. The 2013 Act lists the National Highways Act in its Fourth Schedule, and a 2015 order extended these benefits to it. Our guide on land acquisition compensation calculation explains each step with an example.
Sometimes only a right of use or an easement over the land is taken, not the land itself. The amount is then 10% of the amount fixed for that land.
The evidence that counts
Most highway disputes turn on the sale deeds used. In 2026, the Supreme Court decided NHAI v. Alfa Remidis. The arbitrator had valued industrial land using one sale of a residential plot in another village. The Court held that the average sale price cannot rest on a single sale deed. It applied the stamp duty value instead, which gave the owner less than the arbitrator had awarded.
Ask for a copy of the officer’s order and the list of sale deeds it used. Check each one against your land. Missing deeds of similar land are the most common gap.
The lesson is to bring several sale deeds of similar land, close by, from the three years before the notice. Add:
- the stamp duty rate for your survey number on the notification date;
- every structure, well and tree, measured and photographed;
- evidence of harm to the land you keep, such as lost access to a road, or a strip too narrow to use.
Arbitration under section 3G(5)
If either side does not accept the officer’s amount, it can ask for arbitration. The arbitrator is appointed by the Central Government. The Arbitration and Conciliation Act, 1996 applies to the hearing.
Before the arbitrator, you present your evidence of value and the other side presents theirs. Keep the file in order: the notices, the order, your claim, the sale deeds, the valuation report and photos. If the arbitrator awards more than the competent authority did, they may add 9% a year interest on the excess. It runs from the date of possession until the excess is deposited.
The arbitrator’s award can be challenged in court, but only on limited grounds under the Arbitration Act. A court can set an award aside, for example for patent illegality. So the arbitration is often the main chance to put your evidence on record.
The Act does not set a short deadline for applying, as the 2013 Act does for a reference. Even so, apply promptly. Delay can cost you interest, and your advocate will check the time limits that apply. If you are under the 2013 Act instead, see how to challenge land acquisition compensation.
Solatium and interest for older acquisitions
Section 3J originally said the old Land Acquisition Act, 1894 did not apply to highway acquisitions. That meant no solatium and no interest under that Act.
- September 2019. In Union of India v. Tarsem Singh, the Supreme Court held section 3J unconstitutional to that extent. Solatium and interest became payable on highway acquisitions.
- February 2025. The Court refused NHAI’s request to apply that ruling only to future cases.
- March 2026. The Court dismissed NHAI’s review petition, but set limits. Claims that had become final before 28 March 2008, with nothing pending, cannot be reopened. Where solatium or interest was claimed late, it runs only from the date it was claimed.
If your land was taken between 1997 and 2015, ask your advocate whether your claim is still open.
Tax on highway compensation
Rural farmland is not a capital asset, so its compensation is not taxed as a capital gain. For other land, the Chhattisgarh High Court held in 2025 that section 96 of the 2013 Act also exempts highway compensation. That is not yet settled everywhere. Our guide on land acquisition compensation tax exemption explains the rules, including interest.
Mistakes to avoid
- Not filing a claim with evidence after the section 3G public notice.
- Relying on one sale deed, or on sales of a different kind of land.
- Forgetting to claim for structures, trees and the harm to the land you keep.
- Waiting years before applying for arbitration.
- Assuming an old acquisition cannot carry solatium without checking the 2026 limits.
For highway arbitration or a claim to the competent authority, send us the 3A notification, the award and your land record on WhatsApp. Our land acquisition compensation valuation works out the market value on the date of the 3A notice. The fee is fixed and agreed before work starts. For why the date fixes the number, see our guide on the valuation date in property disputes.